ADU timeline guide

# How Long Does It Take to Build an ADU in San Jose?

By [Sal Taraboulsi, Owner](https://qabuilders.com/author/sal-taraboulsi/) | Published November 17, 2026 | Updated November 17, 2026

[Call (669) 213-8077](tel:+16692138077)

[Free estimate](https://qabuilders.com/adu-timeline-san-jose/#quote)

How long it takes to build an ADU in San Jose does vary by type: from permits to completion, most ADUs take 6-12 months. Garage conversions can be faster (4-6 months), while custom detached units may take up to a year.

On the permit side, the City says the first round of building review typically takes 20 business days when the plans need no additional review. An ADU built from one of the City’s preapproved plans may get its permit on the day of the plan review meeting, if the lot is zoned residential with an existing single-family home or duplex, and outside geohazard, landslide, flood and wildfire (WUI) zones, and the site-specific plan and documents are accurate and complete.

QA Builders handles the design, the City permit and the construction; what each ADU type allows on your lot is on our [ADU builders San Jose](https://qabuilders.com/adu-builders/) page. For a timeline on your property, call [(669) 213-8077](tel:+16692138077) or [ask for a free consultation and estimate](https://qabuilders.com/adu-timeline-san-jose/#quote).

Wooden foundation forms and an open trench for a front addition on a single-story San Jose house

Contents [Get a free estimate](https://qabuilders.com/adu-timeline-san-jose/#quote) [How long each type of ADU takes](https://qabuilders.com/adu-timeline-san-jose/#adu-time-by-type) [Design and site documents: the stage you control](https://qabuilders.com/adu-timeline-san-jose/#design-and-site-documents) [Recent builds by QA Builders](https://qabuilders.com/adu-timeline-san-jose/#recent-builds-by-qa-builders) [City plan review and resubmittals](https://qabuilders.com/adu-timeline-san-jose/#city-plan-review) [Fees and permit issuance](https://qabuilders.com/adu-timeline-san-jose/#fees-and-permit-issuance) [Construction, inspections and move-in](https://qabuilders.com/adu-timeline-san-jose/#construction-and-inspections) [What state law sets](https://qabuilders.com/adu-timeline-san-jose/#what-state-law-sets) [ADU timelines outside San Jose](https://qabuilders.com/adu-timeline-san-jose/#adu-timelines-outside-san-jose) [What ADU and garage conversion clients say](https://qabuilders.com/adu-timeline-san-jose/#what-adu-and-garage-conversion-clients-say) [ADU timeline questions](https://qabuilders.com/adu-timeline-san-jose/#adu-timeline-questions) [Get an ADU timeline for your lot](https://qabuilders.com/adu-timeline-san-jose/#adu-timeline-for-your-lot)

## Get a free estimate

Tell us about your project and one of our representatives will get back to you.

## How long each type of ADU takes

The type of unit sets how much has to be built new and which stage to plan around. The middle column gives the ranges from our ADU page, measured from permits to completion; the last column names the stage and the City rules to plan around for that type.

| ADU type | From permits to completion | The stage to plan around |
| --- | --- | --- |
| Garage conversion (ADU or JADU) | Can be faster: 4-6 months | Plan review and the work inside a structure that already stands. A JADU also needs a deed restriction with a wet signature, mailed to the City, but no separate PG&E meter. |
| Attached ADU | Within the 6-12 months most ADUs take | Design and plan review of the connection to the house. An attached ADU over 500 square feet, with more than 3,600 square feet in total with the main home, means fire sprinklers for the entire house and the ADU. |
| Detached ADU | 6-12 months; custom detached units may take up to a year | Construction of a complete new building and its utility runs, including the separate meter PG&E requires for every ADU. |
| Two-story ADU | No separate figure; custom detached units may take up to a year | Design and engineering: a second story is drawn under the City’s standards, which allow 25 feet for two stories, since the state standards cap a new detached ADU at 16 feet. |
| ADU on a City preapproved plan | No separate figure | The permit stage: on a lot zoned residential with an existing single-family home or duplex, and outside geohazard, landslide, flood and wildfire (WUI) zones, with accurate, complete site documents, the permit may be issued at the plan review meeting; a deferred structural submittal, a clearance or a variance can make it take longer. |

### How long a garage conversion takes

Garage conversions can be faster (4-6 months), since the slab, walls and roof are already there; the City review, the fire and utility rules and the inspections still apply. The choice between an ADU and a JADU, and what the work involves, are on our [garage conversion page](https://qabuilders.com/garage-conversion-san-jose/).

## Design and site documents: the stage you control

San Jose’s ADU process page warns: “City staff will NOT process inaccurate or incomplete plans!” A complete, accurate package is what avoids lost review cycles. How long this stage takes depends on the lot and on how quickly the documents below come together, so we give no figure for it.

What goes into a complete San Jose submittal, in the order the City lists the steps:

1. **The ADU Universal Checklist.** The City highly recommends it as the first step: it shows whether the lot is eligible and which property conditions affect the project, including the hazard zones that rule out a same-day preapproved permit.
2. **Planner feedback, if you want it.** Basic questions go to the Planning Division by phone or email; project-specific feedback is a preliminary virtual meeting with a planner, billed by the hour.
3. **City or state standards.** The City asks for this choice as early as the planner meeting request; it fixes the size, height and siting the plans are drawn to.
4. **Plans and reports.** A plan set to Bulletin 211, the ADU inspection checklist (Bulletin 213), Title 24 energy calculations with the CALGreen checklist, and a geotechnical report where the lot calls for one.
5. **The water flow letter.** Your water company’s letter with the flow at the hydrant closest to the lot. The City notes that projects are often delayed because applicants do not get this letter, and advises doing it early.
6. **Owner forms.** The address assignment request (Form 302) and the ADU property owner declaration (Form 312), signed digitally. A JADU uses the deed restriction agreement (Form 313) instead, which the County Recorder requires to carry a wet signature, so it is printed, signed and mailed.

We navigate San Jose’s permitting process on your behalf, handling all paperwork and inspections. Fire access is worth checking at this stage too: if any part of the ADU is more than 150 feet from the street curb, measured along a clear path at least 4 feet wide to all sides of the ADU, or an exterior wall is more than 600 feet from a fire hydrant, the City says a fire variance with additional safety measures may be needed.

## Recent builds by QA Builders

Real jobs, real photos from our [home additions](https://qabuilders.com/home-additions/) and new-build projects, through the same foundation, framing and inspection stages a new attached or detached ADU goes through. Open a project to see every photo.

New kitchen with long quartz island in a San Jose home addition Home addition Video 625 sq ft front addition with open kitchen San Jose "They were able to skillfully navigate the city’s labyrinthine processes around permits and inspections, and complete a complex job with multiple vendors..." Fazal A. View project → Finished home addition with new windows and stucco in Santa Clara Home addition Video Master suite and bedroom addition Santa Clara View project →

[See all our projects →](https://qabuilders.com/portfolio/)

## City plan review and resubmittals

Once the package is uploaded to SJePlans, the City moves it through three phases: prescreen, plan review and issuance review. At prescreen a permit specialist confirms the application is ready and invoices the initial plan review fees; the plans go to a reviewer only after that invoice is paid.

In the City’s words: “It typically takes 20 business days to go through the first round of building review unless your plan needs additional review.” Twenty business days is four working weeks, more when a City holiday falls inside them. Comments go to the ePlan Applicant, the one person named on the application who uploads files and answers reviewers, and each set of corrections goes back through SJePlans as a new cycle.

Resubmitting plans without making the required corrections “may result in additional review cycles and delays,” the City says, while accurate, complete and corrected plans are what it says keep the review within one or two cycles. Three things the City’s own pages tie to longer reviews:

- a water flow letter that was never requested;
- a resubmittal that leaves some comments unanswered;
- a lot that needs a fire variance, a clearance or another variance, which the City says can slow even a preapproved plan.

Building a new house at the same time? San Jose allows it, but the new house must pass its final inspection before the ADU’s final inspection can take place, so the ADU cannot finish first.

## Fees and permit issuance

Approved plans are not yet a permit. San Jose runs an issuance review once the final invoices are paid:

- residual plan review fees, with taxes;
- inspection fees, with taxes;
- the Building Permit Application Fee (Bulletin 310);
- the owner-builder acknowledgement form (Bulletin 311), only when the owner is the builder;
- school and parkland fees, which do not apply to an ADU under 751 square feet.

When every item is cleared, the City emails that the permit card and approved plans are ready in SJePlans, and construction can start. What the amounts depend on is covered in our [ADU cost guide for San Jose](https://qabuilders.com/adu-cost-san-jose/).

Preapproved plans save the most time here. Their construction drawings were reviewed by City staff before you applied, so the meeting on your project can end with the permit itself. Same-day issuance needs a residentially zoned lot with an existing single-family home or duplex, outside any geohazard, landslide, flood or Wildland-Urban Interface zone; the plan is preapproved, the site is not, so your site plan and documents still decide it.

## Construction, inspections and move-in

With the permit card issued, building starts and the City inspects as the work goes: foundation before concrete, under-slab or underfloor, rough plumbing, mechanical, gas and electrical before anything is covered, framing, lath, insulation, and then the building final, which the City approves only after every other inspection on the permit has passed. For an ADU the City asks that the completed ADU inspection checklist (Bulletin 213) be shown with the approved plans and the permit card.

On an inspection day the inspector calls between 7:00 and 8:00 a.m. and gives a 2-hour arrival window. How San Jose inspections work for any remodel is set out in our [San Jose remodeling permits guide](https://qabuilders.com/san-jose-remodeling-permits/).

Home addition framing with new sliding doors during construction

Three steps sit at the end of the build:

- **The PG&E meter.** PG&E requires every ADU to have its own meter, and the City says to confirm the requirements directly with PG&E, since the City does not set its metering policies. A JADU needs no separate meter.
- **The construction waste sign-off.** The Construction and Demolition Diversion review and sign-off must be complete before the building final is booked.
- **The final itself.** Once construction is complete and the final building inspection is approved, the City considers the ADU ready to move into.

Long builds also run against a permit clock. A San Jose permit without a final inspection expires 12 months after it was issued or 180 days after the last inspection approval or partial approval. A first extension, requested before the permit expires, adds 180 days if approved. A second needs a letter of request to the Chief Building Official, is at that official’s sole discretion, cannot be appealed and may run up to 360 days; no more than two extensions (540 days in total) are allowed.

Every project receives a dedicated project manager so you know who to turn to every step of the way.

## What state law sets

California Government Code 66317 gives every city, San Jose included, deadlines for ADU permit applications. The current text (updated January 1, 2026) sets:

- **15 business days to judge completeness,** counted from when the city receives the application. It must tell you in writing whether the application is complete; if it is not, it must list the missing items and say how to fix them.
- **15 business days again for a resubmittal,** counted from when the city receives the resubmittal (Gov. Code 66317(a)(2)(E)), and the city cannot ask for anything that was not on its list.
- **Deemed complete** if the city misses either deadline.
- **60 days to approve or deny** a complete application when a house already stands on the lot, counted from the day the city receives the complete application; past that, the application is deemed approved. A denial must come within the same period, with written comments on what is deficient and how to remedy it.
- **A pause you control:** if the applicant asks for a delay, the 60 days stop for that period.
- **A new house first:** an ADU filed with a new single-family or multifamily home can wait until the house application is approved or denied.
- **Appeals:** a written appeal of an incomplete finding or a denial gets a final written decision within 60 business days of the city receiving the written appeal.

These are outer limits, not the usual pace. The City’s 20 business days describes a typical first review, and neither figure covers drawing the plans, answering comments or clearing issuance, so neither one is the length of the whole permit stage.

An ADU that already exists without a permit follows a different path. San Jose’s AB 2533 program offers “a clear, penalty-free path to legalize an unpermitted accessory dwelling unit or junior accessory dwelling unit built or converted before January 1, 2020,” and the City says “The process typically takes 4 to 6 months from a complete application.”

Sources: California Government Code 66317; City of San Jose ADU plan review and permit process, ADU FAQs, preapproved ADU and AB 2533 pages, and Bulletin 203; read November 2026.

## ADU timelines outside San Jose

Each city runs its own ADU review within the state deadlines, so the permit stage changes with the address. QA Builders works across the Santa Clara, San Mateo and Alameda County cities we serve; here is what four of them publish about timing.

**Cupertino.** The building permit page lists 10 days for the first review of a detached or attached ADU and 10 days for each resubmittal once an application is deemed complete, while a notice on the same page gives the current average as 20-30 business days for the initial plan review and 10-20 business days for each subsequent review.

Cupertino’s preapproved plans apply only to detached ADUs on parcels in the Valley Floor Zone, and a JADU covenant must be obtained from Planning staff, notarized and recorded with the Santa Clara County Recorder before the final building inspection is scheduled. Our page on [remodeling in Cupertino](https://qabuilders.com/service-areas/cupertino/) covers the city’s ADU size and parking rules.

**Mountain View.** Once an application is deemed complete, the city’s timeline table gives 2 weeks for the first review of a new or conversion ADU or JADU and 2 weeks for each resubmittal; a preapproved detached ADU gets 2 weeks, then 1. Its ADU page also states “Typical Time to Receive Permit: 4 to 6 months”, and no planning permit is required. See [remodeling in Mountain View](https://qabuilders.com/service-areas/mountain-view/).

**Campbell.** An ADU or JADU needs no land use entitlement; the complete application goes straight to the Building Division. For building permits the city asks owners to “allow a minimum of 4 to 6 weeks for the first plan-check and 2 to 4 weeks for all subsequent reviews,” and its ADU Express Plan Check, designed to cut processing to one week, has been temporarily suspended. More on [remodeling in Campbell](https://qabuilders.com/service-areas/campbell/).

**San Mateo.** ADU approval is ministerial, with only a building permit and related permits and no planning application with public notice. For a JADU, City staff draft the deed restriction, which is signed and recorded before the permit is issued. The city’s ADU handout gives no review time. See [remodeling in San Mateo](https://qabuilders.com/service-areas/san-mateo/).

## What ADU and garage conversion clients say

[BuildZoom](https://www.buildzoom.com/contractor/qa-builders-san-jose-ca#reviews)

> "QA Builders just finished an ADU addition for me and they did a phenomenal job. From the very first meeting they were professional, punctual, kind and laser focused on getting the job done well..."

Read the full review →

D **Dinabrown1983**ADU addition

[BuildZoom](https://www.buildzoom.com/contractor/qa-builders-san-jose-ca#reviews)

> "Sal was project manager, he was a true professional, always on time, always ready to help and always available for a contact."

Read the full review →

J **Jon C.**ADU garage conversion

[BuildZoom](https://www.buildzoom.com/contractor/qa-builders-san-jose-ca#reviews)

> "Sal was my project manager and he was honest, professional, communicative and he also save me money with his great suggestions."

Read the full review →

A **Andrew M.**ADU garage conversion

[BuildZoom](https://www.buildzoom.com/contractor/qa-builders-san-jose-ca#reviews)

> "The project they did for me is ADU Garage Conversion, big and complicated project but Sal made it simple as possible and it went very smooth thank to him and his well organized crew."

Read the full review →

J **John R.**ADU garage conversion

[Read more homeowner reviews →](https://qabuilders.com/testimonials/)

## ADU timeline questions

### How long does it take to get an ADU permit and build the ADU in San Jose?

From permits to completion, most ADUs take 6-12 months. Garage conversions can be faster (4-6 months), while custom detached units may take up to a year. In San Jose, the City’s first round of building review typically takes 20 business days when the plans need no additional review, and a preapproved plan with complete site documents may be permitted on the day of its plan review meeting when the lot is zoned residential with an existing single-family home or duplex, and outside geohazard, landslide, flood and wildfire (WUI) zones.

### How long does it take to get a permit for an ADU in California?

State law gives the city 15 business days from receiving an ADU application to decide whether it is complete, and 60 days from receiving the complete application to approve or deny it when a house already stands on the lot; if it misses the 60 days, the application is deemed approved. Real times vary by city: San Jose’s first building review typically takes 20 business days, and Mountain View’s ADU page gives 4 to 6 months to receive a permit.

### How fast can you build an ADU?

Of the types we build, garage conversions can be faster (4-6 months), because the structure already stands. On the permit side, a City preapproved plan with accurate, complete site documents may be permitted on the day of the plan review meeting when the lot is zoned residential with an existing single-family home or duplex, and outside geohazard, landslide, flood and wildfire (WUI) zones; requesting the water flow letter early and answering every review comment in one resubmittal help keep the City review to one or two cycles.

### Can I build an ADU and a new house at the same time?

Yes. San Jose allows both, with rules on the distance between the ADU and the main home, but the new house must pass its final inspection before the ADU’s final inspection can happen. Under state law, the city may also hold its decision on the ADU until it approves or denies the new house.

## Get an ADU timeline for your lot

We handle everything in-house: design, permits, construction, and finishing, so you have one point of contact and one team accountable for your project’s success. QA Builders (CSLB License #1073096) builds ADUs in San Jose and across the Santa Clara, San Mateo and Alameda County cities we serve.

Contact us for a free consultation and estimate: call [(669) 213-8077](tel:+16692138077) or use our [contact page](https://qabuilders.com/contact/).

[Schedule Consultation](https://qabuilders.com/contact/)

[Call Us Now](tel:+16692138077)